Most single-family tear-offs are completed in 1–3 working days. Duration depends on roof size/complexity, the number of layers, decking repairs, weather, and access.
Typical crew & schedule
- Crew size: Usually 4–8 roofers led by an on-site foreman; we may scale to 10+ on larger or time-sensitive projects.
- Day 1: Protection setup (landscaping/driveway), full tear-off of first sections, decking inspection/repairs, underlayment and flashings started, site cleanup before we leave.
- Day 2–3: Finish underlayments/flashings, install shingles, ridge/vents, detail work (pipes, skylights), final cleanup and magnetic nail sweep.
What can extend the timeline
- Multiple layers or heavy shingle weight
- Hidden decking damage/rot requiring replacement
- Complex details (steep pitches, many valleys, dormers, skylights, chimneys)
- Weather holds or municipal inspection timing
- Limited material staging or difficult access
Communication & work hours
- You’ll get the crew arrival window and daily plan each morning, plus an end-of-day recap with photos.
- Standard work hours are shared in advance; we follow HOA/city quiet-hour rules. If an extra day is needed, your roof is fully dried-in overnight.
Larger or special projects
- Large homes, multi-family buildings, or specialty materials (cedar, metal, slate) often run 3–5+ days and may require staggered crews or phased areas.
Bottom line: we size the crew to your project, keep you updated daily, and won’t leave until the roof is watertight and the property is clean.